| Notice to Proceed (NTP) | May 17, 2022 |
| Preliminary Design Submittal | August 30, 2022 |
| Initial Engineering (30% Design) Submittal | February 21, 2023 |
| Public Meeting #1 | March 8, 2023 |
| Constructability Plans (100% Design) Submittal | September 28, 2023 |
| Public Meeting #2 | October 19, 2023 |
| Production (Construction Documents) | January 2024 |
| FDOT Issues Revised Authorization to Bid | October 2024 |
| Revised Invitation to Bid Construction | November 2024 |
| Construction Start Date | May 5, 2025 |